01
RAVS for Transient Fault
Functional Features
1 | Beidou/GPS timing | can be connected to a separate external time synchronization device or shared with the original system clock |
2 | Voltage flicker | If the difference between the maximum peak values of the two adjacent wave heads of the voltage waveform exceeds the set threshold, immediately start recording(-1~+30s ) |
3 | Voltage sag | if the voltage of any phase is lower than the set threshold, immediately start recording(-1~+30s ) |
4 | Voltage oscillation | Oscillation is difficult to prevent and poses serious harm. When the oscillation amplitude exceeds the set threshold, immediately start recording(-1~+30s ) |
5 | Voltage deviation | The transient voltage waveform contains a DC component, and when the amplitude exceeds the set threshold, the recording is immediately initiated(-1~+30s ) |
6 | Voltage surge | External surge, power transmission, protrusion, sudden load rejection, etc., exceeding the set threshold, immediately start recording(-1~+30s ) |
7 | Voltage grounding | When a single-phase grounding fault occurs in the system, accurately identify the fault and its occurrence time, and immediately start recording(-1~+30s ) |
8 | Voltage short circuit | When a phase to phase short circuit fault occurs in the system, accurately identify the fault and its occurrence time, and immediately start recording(-1~+30s ) |
9 | Routine power quality monitoring | Voltage fluctuation, load current, power analysis, THD monitoring, imbalance monitoring, etc No need to install other power quality monitors |
10 | Main spec | Sampling frequency 100kHz; monitor 0-63 harmonics, inter harmonics, and higher harmonics; 4G memory, 64G solid-state drive; LCD high brightness TFT LCD touch screen; 10 inches; Resolution 800 × 600; one × RS-232/485, 1 × RS232, 4 × USB2.0, 1 × VGA, 1 × GigaLAN |
products advantage
No. | items | Main technical features |
1 | Technical level | High sampling frequency: 20kHz(sampling time: 83ms → 50ms)
More duration time recording: --1~+30s (panoramic recording) More duration time when power loss: 60s Accurate time synchronization function: Beidou or GPS Stronger analysis capabilities: Real time analysis of various voltage issues Solution Recommendation: Based on the analysis results of panoramic recording, recommend the most reasonable solution |
2 | Process level | Change the touch screen to 10 inches
Improve wiring methods: wiring terminals, wiring methods, etc High strength anti vibration structural design Artwork style full art design |